- Feature Links
- Current Projects
Current Projects
Ludington Police Department 2025 Community Survey Results & Analysis
-
Invasive Species:
Link to page
UDO Draft
AndyS Construction Project
- 129 W Ludington Weekly Work Update 2
- 129 W Ludington Weekly Work Update 3
- 129 W Ludington Weekly Work Update 4
- 129 W Ludington Weekly Work Update 5
- 129 W Ludington Weekly Work Update 6
- 129 W Ludington Weekly Work Update 7
- 129 W Ludington Weekly Work Update 8
- 129 W Ludington Weekly Work Update 9
- 129 W Ludington Weekly Work Update 10
- 129 W Ludington Weekly Work Update 11
- 129 W Ludington Weekly Work Update 12
- 129 W Ludington Weekly Work Update 13
- 129 W Ludington Weekly Work Update 14
- 129 W Ludington Weekly Work Update 15
- 129 W Ludington Weekly Work Update 16
- 129 W Ludington Weekly Work Update 17
- 129 W Ludington Weekly Work Update 18
- 129 W Ludington Weekly Work Update 19
- 129 W Ludington Weekly Work Update 20
- 129 W Ludington Weekly Work Update 23
- 129 W Ludington Weekly Work Update 06112024
Cartier Park Bathhouse Renovation
Golden Hall Apartments
Foster School Site Development
North Shore Apartments
Tinkham Avenue
- City of Ludington - Tinkham Avenue Reconstruction
- Week Ending April 5: Work on Tinkham Avenue has now begun! Work will continue on this project until early July, please be aware of the posted detour around the site. Access to Oriole Field will be from Lowell Street until further notice.Work Completed Last Week
• Set up traffic control and detour signage.
• Removed the roadway and completed the majority of the concrete removals along the project length.
Anticipated Work This Week• Continue removing concrete from the site.
• Begin installation of water main and sanitary sewer west of Gaylord.
- Week Ending April 12
This was a productive first week of underground work with progress being made on both sanitary sewer and water main. Work Completed This Week • Replaced the sanitary sewer from Park Street to the first alley to the east of Park Street and reconnected all properties. • Installed the water main from Park Street to Ferry Street. Anticipated Work Next Week • Complete testing on the water main from Park Street to Ferry Street, assuming all tests pass, this main should be connected to the system by the end of the week. • Install storm sewer from Lakeshore to Gaylord. • Work on Sanitary sewer may begin from Gaylord to the east by the end of the week.
- Week Ending April 19
Milbocker has made significant progress on the utilities and has now completed all utilities work from Lakeshore to Gaylord.
Work Completed This Week
• Completed the water main between Park and Ferry. • Completed storm sewer west of Gaylord. • Began installation of sanitary sewer from Gaylord to the East. Anticipated Work Next Week • Continue working on sanitary sewer east of Gaylord. • Install storm sewer at Gaylord. • Begin grading the roadway in preparation of curb and gutter from Lakeshore to Gaylord.
- Week Ending April 26
Underground work continued east of Gaylord with both Sanitary Sewer and Water Main. Road rebuilding has also begun west of Gaylord.
Work Completed This Week Sanitary sewer was completed from Gaylord to Lakeview. Water main was installed starting at Lakeview and working east. Storm sewer was installed in the Gaylord intersection. Anticipated Work Next Week Sanitary sewer will be installed from Lewis Street to William Street. Water main will be installed working east from Lakeview. Grading of the sand grade west of Gaylord will continue and aggregate placement will begin.
- Week Ending May 3 Underground work continued with the focus on the sanitary sewer east of Lewis Street. Road rebuilding continued west of Gaylord. Work Completed This Week Sanitary sewer installation continued east of Lewis Street with most work focused at St. Paul to Lewis. Water main was installed up to near Williams. Aggregate placement in preparation of curb and gutter began west of Gaylord. Anticipated Work Next Week Sanitary sewer installation will be completed. Water main installation will be completed less final connections. Aggregate placement will continue. Remaining storm sewer will be completed.
- Week Ending May 10
Underground work continued with the focus on the water main and storm sewer east of Gaylord. Road rebuilding continued west of Gaylord.
Work Completed This Week • Water main installation east of Gaylord. • Road rebuilding with aggregate placement in preparation for curb continued west of Gaylord. Anticipated Work Next Week • Continued work on water main and water services. • Continue work on storm sewer east of Gaylord. • Curb and gutter placement is scheduled early week west of Gaylord. With the beginning of concrete work, access to driveways will not be able to be maintained until the concrete cures. Make sure any vehicle that will need to be used over the next week is removed from your driveway impacted by the work prior to installation of the curb. Please do not write in the concrete or drive across it until the contractor indicates that you may.
- Week Ending May 18 Underground work has essentially wrapped up on the project! Road rebuilding will be the primary focus moving. Significant progress on the road reconstruction was also made with concrete curb and approaches being installed west of Gaylord.Work Completed This Week Utility work is now complete less a few minor finish items. Concrete curb and gutter was completed west of Gaylord. Concrete driveway approaches were completed west of Gaylord. Anticipated Work Next Week Sidewalk ramps will be poured on Monday as well as remaining curb west of Gaylord. Final grading of the gravel west of Gaylord in preperation of paving. Grading for sand grade and spreading of gravel east of Gaylord will begin. Paving of the first layer of asphalt west of Gaylord is possibly by the end of the week but that schedule is not certain.
- https://www.preinnewhof.com/construction_projects/tinkhamavenue/
100 SW Ludington Ave. Alley On Hold
Haskell Project/Lofts on Loomis/ 801 N Rowe COMPLETED
2019 Downtown Rental Rehabilitation COMPLETED
- MEDC Grant Application
- GRANT APPLICATION SECTIONS :
- COL Grant APP
- General Applicant Certification Form
- Background Check Disclosure
- 212 W Ludington Ave Combined App and Pre-app Documents
- 119 W Ludington Ave Combined App and Pre-app Documents
- 327 S James Street Combined App and Pre-app Documents
- SAM CAGE Codes
- MEDC
- MEDC Letter of Interest
- ENVIRONMENTAL
- Exempt Packets for Engineering 119 W Ludington
- Exempt Packets for Engineering 212 W Ludington
- Exempt Packets for Engineering 327 S James
- Engineering Exemptions MEDC
- Environmental Review File for Downtown Rental Rehabilitation
- State Historic Preservation Office Response 327 S James
- State Historic Preservation Office Response 119 W Ludington
- State Historic Preservation Office Response 212 W Ludington
- Combined Notice Rental Rehab
- Re-Evaluation of an Environmental Assessment
N James Street/ Legacy Plaza COMPLETED
- MEDC Grant Application
- MEDC Letter of Interest
- Exempt Packet for Engineering Legacy Plaza
- Engineering Exemption MEDC Legacy Plaza
- Prein & Newhof Professional Services Agreement
- Environmental Review File for N James Street/ Legacy Plaza
- State Historic Preservation Office Response
- Combined Notice Legacy Plaza
Copeyan Park Improvements COMPLETED
West End of Ludington Ave. COMPLETED
- Stearns Park West End Rendering
- Advertisement for Bids
- Addendum 1
- Addendum 2
- Combined Drawings for Bidding
- Specs
- Bid Tabulation
- Hallack Bid
- Tridonn Bid
- Value Engineering
- Pipe Guardrail Shop Drawing
- Durham Benches Shop Drawing
- Northgate Trash Recepticles
- Anchors Rings Screws
- Architectural Contract
- Tridonn Contract